A recent discovery at the 7th Street re-construction project in Terre Haute will push the cost of the work over $500,000.

Posted: Apr 24, 2018 4:00 PM
Updated: Apr 24, 2018 6:32 PM

TERRE HAUTE, Ind. (WTHI) - A recent discovery at the 7th Street re-construction project in Terre Haute will push the cost of the work over $500,000.

The city is rebuilding 7th Street between Hulman and Voorhees.

The contractor will remove the inter-urban rail lines.

The city engineer's office says the sub-base to the east of those lines is weak and must be replaced.

That's to prevent new pavement from falling into disrepair with two years.

The Board of Public Works and Safety approved a change order to the project to cover the additional cost.

The additional cost will total about $95,000.

Article Comments

Terre Haute
Few Clouds
34° wxIcon
Hi: 40° Lo: 23°
Feels Like: 25°
Robinson
Scattered Clouds
34° wxIcon
Hi: 40° Lo: 23°
Feels Like: 24°
Indianapolis
Broken Clouds
30° wxIcon
Hi: 34° Lo: 21°
Feels Like: 17°
Rockville
Broken Clouds
28° wxIcon
Hi: 37° Lo: 21°
Feels Like: 17°
Casey
Overcast
34° wxIcon
Hi: 40° Lo: 22°
Feels Like: 25°
Brazil
Few Clouds
34° wxIcon
Hi: 38° Lo: 22°
Feels Like: 25°
Marshall
Few Clouds
34° wxIcon
Hi: 39° Lo: 23°
Feels Like: 25°
Windy & Colder
WTHI Planner
WTHI Temps
WTHI Radar

Latest Video

Image

Thursday Afternoon Weather

Image

Shamrock 5k Downtown Greencastle, In March 7th

Image

Thursday Morning Weather Update

Image

Domestic violence awareness

Image

Linton Loogootee at BLF

Image

Wednesday Late Forecast

Image

Indiana Gaming Commission not expected to decide on Terre Haute's casino at next meeting

Image

What is Discrimination? ISU Presentation

Image

Cody Zeller special shoes

Image

Hey Kevin 2-26

WTHI Events